Repairs Underway on I-40 Overpass in Lebanon

0
404

Repairs to the I-40 Sparta Pike overpass in Lebanon have begun. An emergency contract was awarded on April 15 and work is expected to be completed by July 15, 2022, just in time for the Tennessee State Fair at the Wilson County Fairgrounds.

The I-40 bridge was damaged on March 10 by a dump truck with its truck bed still raised.

The truck was headed north on Sparta Pike when it struck the bottom of the overpass damaging the concrete beam underneath. In response, the off-ramp of Exit 239B SR-26/US-70/Lebanon-Watertown was closed to traffic and a detour was put in place.

The emergency repair contract was awarded to Mid-State Construction Inc. for $837,418.33. Construction began May 15, which will include alternating, single lane closures on Sparta Pike from 9 a.m. – 3 p.m. and 8 p.m. – 5 a.m. each day to avoid rush hour traffic.

It will also include a weekend-long closure of both northbound lanes of Sparta Pike from 8 p.m. Friday, June 3 to 8 a.m., Monday, June 6 to remove the damaged beam and set the new one. Sparta Pike northbound traffic will use a signed detour that utilizes Maddox Simpson Parkway, US-231, and Tennessee Boulevard.

The overpass has been damaged four times in the last three years; so TDOT has placed additional, lighted vertical clearance signs along the north and southbound lanes of Sparta Pike. Drivers can see the clearance height on three separate signs as they approach the bridge.

Motorists can get the latest construction activity and live streaming SmartWay traffic cameras on their desktop or mobile device, at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any landline or cell phone for travel information.

As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for your destination. Drivers should never tweet, text, or talk on a cell phone while behind the wheel.